Serbia

Follow the tasks required to implement the connection codes in Serbia

Implementation Tasks

Completed
Public Procurement for Assistance in National Implementation Process
9/11/2016 > 30/3/2017
Completed
Analysing the system
14/2/2018 > 27/8/2018
Completed
Forming a final proposal of the current Grid Code
1/1/1970 > 30/9/2019
Completed
Determination of non-exhaustive parameters
24/5/2018 > 24/5/2019
Completed
Public consultations on current Grid Code version
1/1/1970 > 31/8/2018
Completed
Determination of RfG non-exhaustive parameters
1/10/2018 > 1/2/2019
Completed
Determination of DCC and HVDC non-exhaustive parameters
11/3/2019 > 11/5/2019
Completed
National Grid Code structure proposal + methodologies for the non-ehaustive parameters determination
24/5/2018 > 27/8/2018

Documents (RS)

RS EMS | Process
RS-National implementation process_v18.03.2016
Download Meta
Country
RS
TSO
EMS
Status
Ongoing
Topic
Process
Class
Progres reports
Subjects
ConnectionElectrical Energy
Created
18/03/2016
Last Modified
18/03/2016
GET THE MOST POWERFUL NEWSLETTER IN BRUSSELS